Skip to content

Process expertise. Chinese manufacturing. Global perspective.

PREASYS

Production line

Pharmaceutical Sachet & Stick Pack Filling and Packaging Lines

A pharmaceutical sachet or stick pack line forms the flexible pack, meters the prepared product and seals each unit before cutting, checking and collation. The filled pack then becomes the input to cartoning and shipping-case handling. Product behaviour and pack geometry determine the filling and transfer configuration.

Multi-lane primary packing connected to downstream cartoning equipment

Sachet filling, connected to final packing

The forming web becomes a primary pack around a measured quantity of product. Dosing and web movement must leave the sealing area clear before the pack closes. Cutting and discharge then turn the continuous packaging process into individual units for counting and collation.

Powder flow, granule characteristics or liquid behaviour change the feed and dosing requirements. Pack width, filled thickness and seal flanges change how the accepted unit moves downstream. Sachets and stick packs can therefore require different handling even when their nominal contents are similar.

Example project input

This balance assumes a powder sachet. Add feeder hold-up, startup and rejected seals separately. A liquid sachet needs its own metering trial.

2,400

Sachets in the example order

3 g

Powder per sachet

7.2 kg

Powder delivered into finished sachets

From sachet forming to finished packs

Product and primary pack

Specify the product, dose and seal

Multi-lane stick-pack machine with product hopper, dosing lanes and pack-forming section
Multi-lane stick-pack configuration shown. Flat sachets require the corresponding film-forming and sealing configuration.

Match the dosing system to the product

For powders and granules, review flow, bulk density, particle size and the target fill mass. For liquids, review viscosity and the metering path. Confirm the dosing choice with the intended product.

Define the film and seal conditions

Agree pack dimensions, film construction and print registration. Evaluate seal temperature, pressure and dwell time with the actual material, keeping product clear of the sealing area.

Agree acceptance and rejection checks

Define fill-quantity, seal and code checks for the selected format. Establish where a rejected pack is removed before accepted packs reach collation.

Explore sachet filling equipment

Your process, your benefits

The same web index connects dosing, seal condition and the resulting cut pack. That relationship helps distinguish material in the seal from web-tracking or timing faults. After cutting, accepted-pack count and orientation become the link between the filling machine’s output and the cartoner’s demand.

How it works

How do we investigate a contaminated seal?

Record the web position and inspect the seal area immediately after dosing. Change one feed or timing setting at a time and retain the corresponding sealed packs.

How do we check a sachet group before cartoning?

Count accepted packs at the cut and collation points. Run the thickest filled pack through the intended grouping orientation and check the carton opening.

Equipment interfaces

From individual sachets to a packed carton

A filled pack is flexible and has a product-dependent thickness, so collation is more than a nominal width match. The transfer must present the required number of accepted sachets or stick packs in the orientation that the carton-loading method receives. Buffering and line signals manage interruptions between these different operating cycles.

Pack transfer and collation

Agree discharge orientation, sachets per carton and leaflet handling. Test the infeed with actual filled packs, including their thickness and seal flanges, before choosing a top-loading or side-loading arrangement.

Output, buffering and line signals

Match accepted sachets per minute to carton demand. Agree accumulation, stop/start signals and fault recovery so a downstream interruption does not leave the transfer unmanaged.

Discuss line engineering

Coding and verification

Choose the print location and inspection point on the agreed pack. Specify serialization or aggregation when required by the product and destination market.

Explore track and trace

Cartons, cases and pallets

Define case counts and the loading pattern. Bundling is an option when the sales or shipping format needs it; palletizing depends on the required level of automation. The equipment views above link to each machine.

Where this packaging line starts

The line receives a product prepared to its agreed specification. Granulation and drying belong to upstream formulation processing when needed; they are not default steps in every sachet packaging line.

Review your process requirements

Support throughout your project and production

Define the equipment scope

Choose powder, granule or liquid dosing according to the formulation and keep product away from the seal area.

Learn more

Agree the acceptance test

Match the number of lanes and timing of cut packs to collation and cartoning.

Learn more

Prepare for operation

Identify the contact parts and format tooling for Pharmaceutical Sachet Production Lines. Agree access for cleaning, the spares to hold and the operating records the site will need.

Learn more

Knowledge hub

2 resources

Frequently asked questions

Are wet and dry granulation mandatory stages of this packaging line?

No. The packaging line receives product prepared to its agreed specification. Granulation or drying belongs to upstream formulation processing when needed. State whether those operations are included separately rather than inserting them into every sachet route.

Can a powder filler also fill a liquid sachet?

Powders, granules and liquids require different feed and dosing arrangements. Confirm the product properties, dose, pack material and cleaning needs for the selected machine. A shared pack shape does not establish interchangeable product handling.

What determines whether a stick pack can use an existing cartoner?

Compare the actual filled dimensions, stiffness, seal flanges, count and discharge pattern. The collation and infeed must hold the accepted packs in the intended loading orientation. A trial with empty film alone does not represent the filled pack.

How should line output be specified?

State accepted primary packs per minute and packs per carton, then relate that to carton and case demand. Include rejects, accumulation and restart behaviour in the operating assumptions. A primary-pack machine rate is not automatically the output of the complete packaging line.