Skip to content

Process expertise. Chinese manufacturing. Global perspective.

PREASYS

Production line

Turnkey Pharmaceutical Aerosol & MDI Filling Line

A pharmaceutical aerosol filling line connects product dosing, valve closing, the selected propellant-charging method and finished-pack checks. For a pressurized metered-dose inhaler (pMDI), the can, metering valve and actuator must be assessed as one presentation before the filling and assembly sequence is fixed.

Aerosol production equipment connected by a U-shaped conveyor

Overview

The can, metering valve and actuator form the aerosol presentation. Liquid dosing supplies the formulation; valve closing creates the pressure-containing pack; propellant charging follows the selected method. The illustrated through-valve sequence is one arrangement. Bag-on-valve and other charging routes use different component and pressure interfaces, so the finished presentation determines the equipment sequence.

Example project input

Each can receives one valve at one setting. Add separate samples for leak and spray testing. Propellant handling depends on the specified pack.

24

Valve assemblies in a setup trial

3

Crimp settings to compare

72

Cans and valves to set aside

From aerosol filling to finished packs

Process requirements and equipment options

Connect the selected filling, valve and test arrangement with downstream packaging. Define the aerosol system before choosing its charging sequence.

Equipment options are shown in process order. Cartoning format, coding and verification are selected for the pack; bundling and palletizing are optional. The final configuration is defined around the product and project scope. The filling image is a configuration illustration.

01 / Filling, closure & testing

Product, can, valve and propellant define the charging route. The sequence below illustrates a conventional through-valve charging route; BOV and other filling methods require a different arrangement.

Prepare cans and components

Confirm the can finish, valve, seals and incoming component condition. Define the product and propellant supply interfaces.

Dose the product

Establish the product fill quantity and compatible filling path for the selected formulation.

Insert and crimp the valve

Match the valve and can finish. Establish the closing settings and the crimp checks for the selected components.

Charge the propellant Selected charging route

For the illustrated route, charge through the closed valve. The charging method, gas handling and installation provisions must match the product and propellant.

Weight and leak checks

Agree fill-weight and leakage checks, rejection and any drying requirement. Select the test method for the product and container.

Actuator and cap assembly

Fit the specified actuator and protective cap after the applicable checks, then transfer the accepted can to packaging.

02 / Cartoning

Match the accepted primary pack, leaflet and carton to the infeed and loading method.

03 / Identification

Agree the print location, readable code and verification method for the destination market.

Code and verify Market dependent

Specify batch coding and, when required, serialization and aggregation. The print and inspection positions depend on the pack.

04 / Bundling

Add a bundle only when the selected sales or shipping pack needs one.

Group cartons Optional

Choose the bundle count and wrapping material. A route without bundling can pass accepted cartons directly to case packing.

05 / Case packing

Transfer cartons or bundles into the agreed shipping-case pattern.

Load the case

Confirm the product arrangement, case construction and the handoff to sealing and pallet handling.

06 / Palletizing

Connect accepted cases to the selected pallet pattern and dispatch interface.

Build the pallet Automation option

Agree case orientation, layer pattern, pallet dimensions and the transfer to warehouse or dispatch.

Filling technologies

The following principles concern liquid-product metering only. Suitability depends on the formulation and selected contact path; these cards do not describe propellant charging or establish that every principle is included in a supplied aerosol line.

Filling technology

Peristaltic pump

A flexible tube carries the liquid while rotating rollers control dosing. The product contacts the tube rather than the pump mechanism. This principle is used when a disposable product path and gentle handling are priorities. Tubing selection, product compatibility and the changeover procedure should be reviewed for each application.

Explore technology
Diagram connecting a peristaltic pump to the product filling path

Filling technology

Piston pump

A piston draws liquid into a cylinder and then dispenses a measured volume through the outlet. The selected piston, valve and product-contact materials determine the application range. Review viscosity, cleaning requirements and the required filling volume together with the product and container format.

Explore technology
Rotary piston metering equipment connected to a set of filling heads

Filling technology

Time pressure

Controlled pressure moves liquid through a filling valve. The opening time and supply conditions determine the dispensed quantity. Product properties, pressure stability and the valve configuration are evaluated together when setting up the filling process.

Explore technology
Diagram of a time-pressure dosing vessel and filling heads

Filling technology

Mass flow

A flow sensor measures the product passing through the filling path and provides feedback to the dosing valve. The process is evaluated around the required fill mass, product behaviour and cleaning strategy. Sensor selection and the control sequence depend on the application.

Explore technology
Product flow path with a mass flow meter and dispensing points
Technology 1 of 4

Your process, your benefits

A leak result is more useful when it remains linked to the can and valve lot, crimp setting and charging conditions. This trace separates component variation from a closing or charging issue. Weight and leakage checks address different properties of the pack, while spray or delivered-dose tests evaluate the assembled presentation under their own test conditions.

How it works

How do we compare crimp settings?

Keep can and valve lots fixed, identify each trial setting and retain the finished samples. Compare crimp measurements and the agreed leak-test result before changing another setting.

How do we check transfer into cartoning?

Run the finished can with its actuator and cap fitted. Observe tipping, actuator contact and how the reject path separates a failed can from accepted packs.

Line integration

Agree the aerosol presentation before connecting the machines: product dosing, valve closing and propellant charging are not interchangeable steps. Define utilities and installation requirements for the selected propellant, then match accepted cans to actuator assembly and packing.

01

Incoming product and format

Choose the can, valve and actuator together. The valve geometry sets the handling and crimp tooling.

02

Process and inspection

Agree where filling, valve placement and crimping occur, then identify the station that verifies the closed pack.

03

Discharge and packing

Release accepted cans to actuator fitting and cartoning. Define how rejects leave the pressurised pack flow.

Support throughout your project and production

Define the equipment scope

Valve design and the selected propellant system determine which charging and checking stations are required.

Learn more

Agree the acceptance test

Prove the transfer from closure to leak and functional checks with the intended can and valve.

Learn more

Prepare for operation

Identify the contact parts and format tooling for Pharmaceutical Aerosol Production Lines. Agree access for cleaning, the spares to hold and the operating records the site will need.

Learn more

Knowledge hub

2 resources

Frequently asked questions

Is a pMDI the same line as a nasal spray or soft mist inhaler?

No. A pMDI uses a pressurized pack and a metering valve. A nonpressurized nasal spray or soft mist inhaler has a different liquid path, closure and device assembly sequence. Select the route using the finished device specification rather than the word spray alone.

Which information determines the charging arrangement?

Provide the formulation, propellant specification, can and valve drawings, required fill quantities and the intended charging method. Review compatibility, handling provisions and the installation boundary with the equipment and site teams. A through-valve route should not be assumed for every aerosol system.

Do fill-weight checks establish inhaler dose performance?

Fill weight checks the material placed in the pack. Metering-valve operation and delivered spray or dose performance require their own agreed tests using the intended formulation, actuator and operating method. Define which checks are inline and which are laboratory or sampled tests.

What should the handoff into packaging include?

Agree the state of the can after testing, actuator and cap fitment, orientation, reject handling and any quarantine requirement. Trial the accepted finished pack in the carton infeed so guides do not damage the valve or accidentally actuate the device.